Reading: Abuja Airport: FCTA to pay N825.8m compensation for construction of 2nd runway – Wike
Share
Aa
Africa Housing NewsAfrica Housing News
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
Search
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Have an existing account? Sign In
Follow US
Africa Housing News > Blog > News > Abuja Airport: FCTA to pay N825.8m compensation for construction of 2nd runway – Wike
News

Abuja Airport: FCTA to pay N825.8m compensation for construction of 2nd runway – Wike

By Author
Last updated: 2023/08/30 at 7:26 AM
By Author Published August 30, 2023
Share
SHARE

Mr Wike said that the amount would be paid through the Federal Capital Development Authority (FCDA) for compensation and resettlement of the people of the community affected by the project.

The Minister of the Federal Capital Territory (FCT), Abuja, Nyesom Wike, says the FCT Administration (FCTA) will pay N825.8 million as compensation for the construction of second runway for Nnamdi Azikiwe International Airport, Abuja.

Contents
Mr Wike said that the amount would be paid through the Federal Capital Development Authority (FCDA) for compensation and resettlement of the people of the community affected by the project.Sources:Premiumtimesng

Mr Wike stated this in Abuja on Tuesday, while briefing journalists at the end of a closed-door meeting with members of the Jiwa community and other stakeholders.

He said that the amount would be paid through the Federal Capital Development Authority (FCDA) for compensation and resettlement of the people of the community affected by the project.

He added that as part of the incentive, 12 people from the community would be employed by the Ministry of Aviation and Aerospace Development and its agencies and 10 by FCTA.

He added that the government would also construct the Tunga Madaki bridge along with a five-kilometre road from the bridge to the community for easy movement of the people.

The minister explained that the project would be captured in the 2024 budget of the FCTA.

Mr Wike also said that FCTA would equally provide a modern health facility to provide quality health care services for people of the community.

He said that an undertaking would be signed based on the agreement between the government and the community.

He identified the signatories as the permanent secretaries of FCTA and ministry of aviation, the Chief of Jiwa, the Chairman, Abuja Municipal Council and the Commissioner, Public Complaint Commission.

“If that is done today, and tomorrow or next tomorrow the money is paid to them, contractors will no longer delay. They have to move to the site immediately and commence work.

“So, the second runway has come to stay,” he said.

He said that the current administration was determined to ensure that the second runway was delivered.

He commended the Chief of Jiwa, Isa Idris, for mobilising his people to attend the meeting to resolve the crises.

Minister of Aviation and Aerospace Development, Festus Keyamo, said that he met the issue on his table, adding that the project ought to have been delivered in July.

Mr Keyamo said that the contractors could not be mobilised because of the issue of compensation.

Earlier, the Permanent Secretary, FCTA, Olusade Adesola, said that the completion of the project requires the support of all relevant stakeholders.

Mr Adesola commended Mr Wike for the intervention to ensure a quick resolution of the issue.

Emmanuel Meribole, Permanent Secretary, Ministry of Aviation and Aerospace Development, said that the project was approved by the Federal Executive Council in March 2022.

Mr Meribole said that the project was awarded to four contractors in April, with CCECC Nigeria Limited as the major contractor.

He, however, said that the project was stalled because of the disagreement over compensation to the affected community members.

Earlier, the Chief of Jiwa, said that the ministry of aviation through its consultant had earlier pegged the compensation at N2.5 million per hectare, for the 12,000 hectares allocated for the project.

Mr Idris further said that the amount was later reviewed downward to N700,000 per hectare when FCTA took over the discussion as the rightful authority to determine how much compensation to be paid.

He said that the community took the matter to the Public Complaint Commission with a view to resolve the issue amicably.

The community leader said that his people were concerned that the N700,000 being offered per hectare would not be enough for the affected persons to acquire another land.

Sources:Premiumtimesng

You Might Also Like

FG Tax Reforms Set to Ease Pressure on Property Market, Encourage Affordable Housing

Umuahia Children’s Centre Cries Out for Government Support as Conditions Worsen

Senate to Host National Security Dialogue as Violence Escalates Nationwide

FG Begins Overhaul of NYSC, Proposes Specialized Teachers and Medical Corps

Naira Strengthens Slightly Against Dollar in Both Official and Parallel Markets

Join Our Whatsapp Group

Contact Image

Join Our WhatsApp Channel

Housing TV Africa is the First Housing News Television
in Africa on Startimes Channel 149 bringing you
Housing News, Mortgage News, Construction News etc

TAGGED: Africa housing news, CCECC, Construction, Federal Capital Development Authority (FCDA), Federal Ministry of Aviation, Housing, Latest Housing News & Updates - Africa Housing News, news, nnamdi azikiwe, real estate, Wike
By Author August 30, 2023 August 30, 2023
Share this Article
Facebook Twitter Email Print
1 Comment

Leave a Reply

Your email address will not be published. Required fields are marked *