Reading: Gridlock: Work resumes on Bwari/Dutsen Road, Abuja in 3 weeks
Share
Aa
Africa Housing NewsAfrica Housing News
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
Search
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Have an existing account? Sign In
Follow US
Africa Housing News > Blog > News > Gridlock: Work resumes on Bwari/Dutsen Road, Abuja in 3 weeks
News

Gridlock: Work resumes on Bwari/Dutsen Road, Abuja in 3 weeks

Fesadeb
Last updated: 2020/09/27 at 8:47 AM
Fesadeb Published September 27, 2020
Share
SHARE

The Federal Capital Territory Administration (FCTA) said work will resume on the Bwari/Dutsen Road, Abuja in three weeks to ease the perennial gridlock in the area as the Administration has concluded arrangements to mobilize contractor to site.
The Executive Secretary, Federal Capital Development Authority (FCDA) Umar Jibrin who stated this when he led some top management staff for on the spot assessment of the road, noted that the project was impeded by the incessant rain fall ,but has to be completed to relieve residents of the stress.
Jibrin explained that the projects, involving full dualisation of the roads, were not abandoned as speculated by residents, but suffered some set back, due to the COVID 19 and some other challenges.
“When we say completion, we are talking of the totality of what needs to be done here. We have some drainage works to be done and other complimentary works.
“But the one that will satisfy the traffic movement is something that can be done in then next two months. In the next three weeks the contractor will demobilize here. We can never do anything when the rain is here.

“We are only coming to appreciate the level at which the rain has impacted on the road. Now that we are going down, the rain is subsiding, the contractor had to come back and do this work in a very short time. The project is not abandoned. Everything is on cause, the contractor is on-ground” the Executive Secretary said.

Credit: Businessday.ng

You Might Also Like

NUPRC, Indigenous Oil Producers Strengthen Alliance to Boost Transparency, Output

NNPCL Reports ₦5.89 Trillion Revenue and ₦748 Billion Profit for April 2025

FG Moves to Enforce Intellectual Property Protection for Nigerian Creatives

Jet Set Nightclub Owners Arrested After Deadly Roof Collapse Kills 236 in Dominican Republic

Ondo Governor Aiyedatiwa Forwards 12 Commissioner Nominees to State Assembly

Join Our Whatsapp Group

Contact Image

Join Our WhatsApp Channel

Housing TV Africa is the First Housing News Television
in Africa on Startimes Channel 149 bringing you
Housing News, Mortgage News, Construction News etc

TAGGED: abuja, Road Construction
Fesadeb September 27, 2020 September 27, 2020
Share this Article
Facebook Twitter Email Print
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

© Africa Housing News. All Rights Reserved 2024

Welcome Back!

Sign in to your account

Lost your password?