By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
Africa Housing NewsAfrica Housing News
Notification Show More
Aa
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Reading: South Africa: Company Leaves R164 Million Housing Project Unfinished
Share
Aa
Africa Housing NewsAfrica Housing News
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
Search
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Have an existing account? Sign In
Follow US
Africa Housing News > Blog > News > South Africa: Company Leaves R164 Million Housing Project Unfinished
News

South Africa: Company Leaves R164 Million Housing Project Unfinished

Fesadeb
Last updated: 2019/07/30 at 11:56 PM
Fesadeb Published July 30, 2019
Share
SHARE

Nophakamile Qongwana is 75 years old. Two months ago she moved into an RDP house for the first time, even though the house in Daluxolo, Madantsane, was not finished.

She said she was excited when she was approved for a house in 2012. Construction started in 2015. The Siyavuna Housing Project was meant to build 88 houses in Daluxolo. Then the company left in late 2015, leaving 55 houses, but without roofs, windows or doors. Construction resumed in 2017 and roofs, windows and doors were added. But water and electricity were not connected.

Fed up with waiting, residents decided to occupy their homes. Qongwana said she waited for an official handover, but none came.

“At least the houses were numbered, hence I could identify which one is mine,” said Qongwana. Then she saw that one of her home’s windows was broken. She decided to move in. She was the last to occupy the houses.

She had been living in a shack since 1985. “My mother died living in a shack. I was 46 when she died in 1990. She dreamed of having a decent house but she never got one.”

The houses were part of a much bigger housing project. In 2014, a R164-million tender to build over 900 houses was awarded to Johannesburg-based company Siyavuna Trading, a close corporation owned by Thembekile Cynthia Mnisi.

Houses were going to be built in Walter Sisulu, Francis Mel, Hani Park, Winnie Mandela, Mahlangu, Gwentshe, Mathemba Vuso and Daluxolo informal settlement.

In 2015 GroundUp reported that the workers at this company were on strike because they claimed they were earning less than R100 per day. In 2017 we reported the slow progress of this housing project, and our failed attempt to get comment from the company. Last year the company went into voluntary liquidation.

We tried to phone Siyavuna to get comment, but the number has been changed and the automated Telkom operator provides no new number.

Siyavuna only built 55 of the 88 houses meant for Daluxolo, leaving 33 families who are still in the dark about their houses. One of them, Lindeka Makeka, 67, has lived in the informal settlement since 1991 and shares a leaking, two-roomed shack with her three elder children and six grandchildren.

“I’ve been holding a house number, but there’s no sign of a house. What frustrates me mostly is that no one tells us anything, including our ward councillor. It looks like he is in the dark … No one is giving us answers,” said Makeka.

“As old as we are, we had a protest here before the election [May 2019], closing the roads with burning tyres demanding answers about our houses. The municipal official who came here promised to attend to us after elections, but we are still here and he never came back,” said Makeka.

Ward councillor Mashwabade Gcilishe (ANC) said some of the houses were left at foundation level because they were built on top of a sewerage pipe. He said a construction company has been hired to install another mini-sewerage system to make sure the current sewerage pipe does not affect the houses.

Meanwhile Qongwana and other residents currently relieve themselves in the bushes. The whole area has six toilets, but four of the toilets are blocked. Some occupiers have made illegal electricity connections. For water, they share a standpipe with an informal settlement.

Questions sent to Buffalo City Metropolitan Municipality spokesperson Bathandwa Diamond and Samkelo Ngwenya last week Thursday were not answered.

Source: allafrica

You Might Also Like

Umuahia Children’s Centre Cries Out for Government Support as Conditions Worsen

Senate to Host National Security Dialogue as Violence Escalates Nationwide

FG Begins Overhaul of NYSC, Proposes Specialized Teachers and Medical Corps

Naira Strengthens Slightly Against Dollar in Both Official and Parallel Markets

Tinubu Inaugurates NASC Leadership, Appoints New Permanent Secretaries

Join Our Whatsapp Group

Contact Image

Join Our WhatsApp Channel

Housing TV Africa is the First Housing News Television
in Africa on Startimes Channel 149 bringing you
Housing News, Mortgage News, Construction News etc

Fesadeb July 30, 2019 July 30, 2019
Share this Article
Facebook Twitter Email Print
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

© Africa Housing News. All Rights Reserved 2024

Welcome Back!

Sign in to your account

Lost your password?