Reading: LEAKING ROOF: FCDA Explains Why NASS Building Cannot Be Fixed Now
Share
Aa
Africa Housing NewsAfrica Housing News
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
Search
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Have an existing account? Sign In
Follow US
Africa Housing News > Blog > News > LEAKING ROOF: FCDA Explains Why NASS Building Cannot Be Fixed Now
News

LEAKING ROOF: FCDA Explains Why NASS Building Cannot Be Fixed Now

Fesadeb
Last updated: 2021/06/30 at 7:06 AM
Fesadeb Published June 30, 2021
Share
SHARE

By Omosola Akingboye, 25th June, 2021

Having come under intense scrutiny and condemnation in some quarters following the embarrassing situation midweek when senators abruptly suspended sitting due to a downpour that affected the National Assembly Chamber, the Federal Capital Development Authority FCDA has explained why it cannot immediately fix the NASS leaking roof or do a total rehabilitation of the complex, saying the contract for the project is currently undergoing procurement processes.

According to Richard A. Nduul, Head, Public Relations and Information at the FCDA in a statement on Friday, said the management of the National Assembly had in 2019 approached the FCDA for a total rehabilitation of the facility.

The statement reads; “The attention of the Federal Capital Development Authority FCDA has been drawn to the recent flooding of the lobby of the National Assembly Complex, Abuja resulting from leakages from the roof. Our findings show the leakages are traceable to blockages of drainages leading to seepage of water through expansion joints in the roof slab.

“Full waterproofing of the roof of the White House building is a major aspect of the proposed renovation of the National Assembly Complex.

“The Management of the National Assembly approached the FCDA in 2019 for a total rehabilitation and upgrading of the NASS Complex to bring it in tune with Parliamentary Buildings around the world.

“This contract is currently undergoing procurement process in line with the Procurement Act of 2007 and will therefore be awarded as soon as it is concluded in conformity with the Act and also considering all other relevant parameters.
“The Authority (FCDA) therefore assures that when the time comes, this project will be executed meticulously in order to ensure that the Nation gets value for the funds that will be expended as this has been the tradition with every other assignment which the Authority has undertaken”.

By design, all public buildings in the nation’s capital including the Presidential Villa are under the purview of the FCDA in terms of maintenance.

You Might Also Like

HDAN Hails Shehu Osidi @ 60: A Man of Vision

Umuahia Children’s Centre Cries Out for Government Support as Conditions Worsen

Senate to Host National Security Dialogue as Violence Escalates Nationwide

FG Begins Overhaul of NYSC, Proposes Specialized Teachers and Medical Corps

Naira Strengthens Slightly Against Dollar in Both Official and Parallel Markets

Join Our Whatsapp Group

Contact Image

Join Our WhatsApp Channel

Housing TV Africa is the First Housing News Television
in Africa on Startimes Channel 149 bringing you
Housing News, Mortgage News, Construction News etc

Fesadeb June 30, 2021 June 30, 2021
Share this Article
Facebook Twitter Email Print
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

© Africa Housing News. All Rights Reserved 2024

Welcome Back!

Sign in to your account

Lost your password?