Reading: Abia to Partner World Bank to Tackle Flooding in Aba
Share
Aa
Africa Housing NewsAfrica Housing News
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
Search
  • Home
  • News
  • Real Estate News
  • Nigeria Property News
  • Join Us
    • About Us
    • Contact Us
    • Join Us
Have an existing account? Sign In
Follow US
Africa Housing News > Blog > News > Abia to Partner World Bank to Tackle Flooding in Aba
News

Abia to Partner World Bank to Tackle Flooding in Aba

Fesadeb
Last updated: 2019/09/03 at 8:48 AM
Fesadeb Published September 3, 2019
Share
SHARE

Abia government has announced collaborative plans with the World Bank to check the flood ravaging Aba, the commercial centre of the state. Abia State Coordinator, Nigerian Erosion and Watershed Management Project (NEWMAP), Mr Izuchukwu Onwughara made this known in Aba while speaking with Newsmen.

Onwughara said that the World Bank had mapped out some of the flooding sites that posed the highest danger to the city to tackle.

He said Obohia roads such as  Uratta axis, Ngwa road and some parts of Port Harcourt road would be tackled in the first phase, while Omuma road and Ohanku road would feature in the second phase.

Onwughara said the projects would be substantially funded by the World Bank with Abia government providing counterpart funding to partner in the project to manage flooding in Aba. The coordinator, who said the project whose duration “is 30 months, will commence by October’’. “We are at very last leg of the preparation of the project in 2019, a lot of consultants came in to do some socioeconomic studies, we did the environmental and social management, we did the resettlement action plan for a project of such magnitude

. “The entire soil investigation has been done; we prepared a design that is of world class standard deploying best practices globally. “The designs have gone through layers of approval from here to Washington and came out cleared. “The job is too big so we’ve split it into two units; we will start with Uratta and Umuagbai and this will cover sections of Port Harcourt, Obohia roads and it will be taken down to Ngwa road. “The advert has been done to pick contractors that will do this project, the valuation of the bids has been concluded and the reports have been forwarded to the World Bank.

“This month, September, we are awaiting their “no objection” response to the report to show it is okay. “We are using this period to sensitise our people to prepare and get ready for the project. “Everyone along the corridors of this project have been consulted and we call on everyone to cooperate with us on this,” he said. Onwughara said that by October the contract for the project would awarded to ensure it took off accordingly.

He called on the residents of Aba to see the project as their own and to give the project handlers their maximum cooperation to ensure its realisation. He said the project was devoid of political interferences because the World Bank was investing heavily in it and would want not to see its funds “go down the drain’’. He said the World Bank worked with the procurement team to ensure global best practices were adopted to make the project successful. He stressed that every step of the project passed through the bank’s approval which resulted in an acceptable bid document after a rigorous process.

“Let me give you some of the contents; for instance, we want a cash flow of up to N3.6 billion for any contractor that will be able to bid for this project. “We want an annual turnover of eight million dollars for the past five years for any contractor that will bid for the project. “We want evidence of two similar projects in the past five years executed by such a contractor. “That advert was on for three months, but only 14 contractors were able to return our bid; about 26 contractors picked our forms and the criteria separated the boys from the men.

“At the day of returning of the bid, we found out that even three were deficient because you have to provide a bid security of seven million naira and people who don’t want to take that risk didn’t come,” he said. He said the project was being assisted by the Nigeria Society of Engineers and procurement consultants from outside Abia did a thorough evaluation of the bid. He said that the bid evaluation report had been the World Bank, adding that the bank was not taking the project lightly and could not allow it to be infiltrated by politicians.

Source: vanguardngr

You Might Also Like

Umuahia Children’s Centre Cries Out for Government Support as Conditions Worsen

Senate to Host National Security Dialogue as Violence Escalates Nationwide

FG Begins Overhaul of NYSC, Proposes Specialized Teachers and Medical Corps

Naira Strengthens Slightly Against Dollar in Both Official and Parallel Markets

Tinubu Inaugurates NASC Leadership, Appoints New Permanent Secretaries

Join Our Whatsapp Group

Contact Image

Join Our WhatsApp Channel

Housing TV Africa is the First Housing News Television
in Africa on Startimes Channel 149 bringing you
Housing News, Mortgage News, Construction News etc

Fesadeb September 3, 2019 September 3, 2019
Share this Article
Facebook Twitter Email Print
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

© Africa Housing News. All Rights Reserved 2024

Welcome Back!

Sign in to your account

Lost your password?